WQ97563 (e) Wedi’i gyflwyno ar 13/10/2025

A wnaiff yr Ysgrifennydd Cabinet roi diweddariad ar ba drafodaethau y mae'n eu cael gyda UK Highways A55 Ltd ynglŷn â'r gwaith atgyweirio i Bont y Borth?

Wedi'i ateb gan Ysgrifennydd y Cabinet dros Drafnidiaeth a Gogledd Cymru | Wedi'i ateb ar 15/10/2025

My officials are in daily contact with UK Highways A55 Ltd.  Work will commence this week (w/c 13 October 2025) to undertake a temporary bridging beam underneath the Menai Suspension Bridge.  This work is expected to be complete by the end of the month.  This will then allow the traffic management to revert to 7.5 tonne and two-way flow.  Work to repair the bolt issue will commence in November. The Phase two works will then recommence following the bolt repairs.