WQ96862 (e) Wedi’i gyflwyno ar 07/07/2025

A wnaiff yr Ysgrifennydd Cabinet roi'r wybodaeth ddiweddaraf am ba waith a wnaed i wella diogelwch cyffordd Rhos-goch ar yr A477?

Wedi'i ateb gan Ysgrifennydd y Cabinet dros Drafnidiaeth a Gogledd Cymru | Wedi'i ateb ar 09/07/2025

Design has been completed for ARAF/SLOW markings and enhanced road signs with yellow backing boards and for a first in Wales, the use of large static bollards to highlight the junction position. The Road Safety Audit 1&2 is due to be completed for these designs.

A topographical survey has been completed for a potential police monitoring lay-by and work started on the design to see whether it is possible to safely accommodate a monitoring layby within our highway land boundary.   

Funding is available for the design process and construction of these short-term measures this financial year 25/26 – in the case of the monitoring layby it will be conditional on not requiring third party land.