WQ93979 (e) Wedi’i gyflwyno ar 16/09/2024

Pa brosiectau ffyrdd a gymeradwywyd gan Lywodraeth Cymru sy'n gor-redeg eu dyddiadau cwblhau ar hyn o bryd, a faint mae'r oedi ar gyfer pob prosiect yn ei gostio i Lywodraeth Cymru?

Wedi'i ateb gan Ysgrifennydd y Cabinet dros Drafnidiaeth a Gogledd Cymru | Wedi'i ateb ar 20/09/2024

The A40 Llandewi Velfrey to Redstone Cross and the A465 sec 5&6 on the Strategic Road Network are currently running to programme and consequently there are no costs for delay. 

The Welsh Government provides funding to some Local Authority road projects through the Local Transport Fund and Resilient Roads Fund. There have been delays in completion of the replacement of the B5065 road in Newbridge, which was initially estimated for completion in winter 2022. These delays have not resulted in an increase in the total amount of funding awarded to the project by Welsh Government.