WQ92546 (e) Wedi’i gyflwyno ar 22/04/2024

A wnaiff yr Ysgrifennydd Cabinet ddarparu llinell amser wedi'i diweddaru ar gyfer y gwelliannau arfaethedig i gyffordd Mynegbost Nash ar yr A477?

Wedi'i ateb gan Ysgrifennydd y Cabinet dros Ogledd Cymru a Thrafnidiaeth | Wedi'i ateb ar 25/04/2024

The scheme to provide junction enhancements, including new traffic light signals at A477, Nash Fingerpost junction is progressing with a view to be operational by end of summer 2024.

The traffic light signals design is now complete and the street lighting design is being reviewed and finalised.

Early contractor involvement has commenced to assist, streamline and minimise disruption for when works commence on site.

The temporary speed limit traffic order process has been completed and new temporary signs for the reduced speed limit for 40mph are in place on approach to the junction. The permanent speed limit order process is underway and is being progressed.

Subject to contractor availability and delivery of specialist technology equipment, our intention is to achieve installation and operation of the permanent traffic light signals at the earliest opportunity.