WQ89410 (e) Wedi’i gyflwyno ar 20/10/2023

Beth yw amcangyfrif presennol Llywodraeth Cymru o gyfanswm cost trydaneiddio llinell arfordir gogledd Cymru?

Wedi'i ateb gan Y Dirprwy Weinidog Newid Hinsawdd | Wedi'i ateb ar 31/10/2023

Rail infrastructure is a reserved matter and is the responsibility of the UK Government. We are not aware that any detailed work has been undertaken by them to provide an accurate estimate of the cost of delivering this scheme. Our own very early indicative estimates suggest that the work necessary to deliver electrification of the entire North Wales Main Line would cost far in excess of the £1bn announced by the UK Government.