WQ86238 (e) Wedi’i gyflwyno ar 06/10/2022

A wnaiff y Gweinidog roi'r wybodaeth ddiweddaraf am y fferm solar arfaethedig ym Maes Awyr Caerdydd?

Wedi'i ateb gan Y Gweinidog Newid Hinsawdd | Wedi'i ateb ar 12/10/2022

The proposed development of East Aberthaw Solar Farm (35MW)  on land at Fonmon, to the west of Cardiff Airport, is at pre-application stage in the Developments of National Significance (“DNS”) process.  As the Welsh Ministers are responsible for determining DNS applications, I am unable to provide any further comment on the proposal. A report will be prepared and submitted to me in due course by Planning & Environment Decisions Wales. As the proposal progresses through the statutory process, updates will be made available on the PEDW website.

The Vale of Glamorgan Council approved a planning application by Cardiff Airport for a 1MW solar farm in July 2020. If you require further information on this scheme or updates on its progress, I advise you contact the Vale of Glamorgan Council.