WQ83653 (e) Wedi’i gyflwyno ar 20/10/2021

A wnaiff y Gweinidog roi'r wybodaeth ddiweddaraf am gynnydd a chost prosiect ffordd Blaenau'r Cymoedd, gan gynnwys dyddiad i'w gwblhau?

Wedi'i ateb gan Y Gweinidog Newid Hinsawdd | Wedi'i ateb ar 26/10/2021

The Heads of the Valleys dualling scheme was split into six sections to enable a phased delivery. Sections 1, 3 and 4 have been completed. Sections, 2 5 and 6 are currently under construction.

Section 4 Tredegar to Dowlais Top

  • Opened November, 2004
  • Cost £47m

Section 1 Abergavenny to Gilwern

  • Opened May, 2008
  • Cost £60m

Section 3 Brynmawr to Tredegar

  • Opened September 2015
  • Cost £158 million (Part-Funded by circa £78m of EU funding from the European Regional Development Fund).

Section 2 Gilwern to Brynmawr

  • Remains on target for completion this year.
  • Cost £336m

Sections 5 and 6 Dowlais Top to Hirwaun

  • End date: 2025
  • Cost £590m