A wnaiff y Gweinidog gadarnhau dyddiad cwblhau disgwyliedig yr atgyweiriadau i ffordd osgoi Aberhonddu ar yr A470, a phryd y caiff y conau traffig eu symud?
Wedi'i ateb gan Y Dirprwy Weinidog Newid Hinsawdd | Wedi'i ateb ar 07/09/2021
Following a competitive tendering exercise, a contractor has been appointed to carry out the geotechnical repair works on the slope above the A40 and also undertake the enhanced embankment maintenance works to improve resilience on this stretch of the trunk road.
The contractor is currently preparing to commence site access and construction works with a planned completion date of the end of November 2021. On completion all traffic management will be removed and the road returned to two lanes in both directions.