WAQ79079 (e) Wedi’i gyflwyno ar 11/11/2019

Ymhellach i WAQ78791 a wnaiff y Gweinidog egluro a oes raid i'r awdurdod lleol dalu'r 75 y cant o gost y cynllun atal llifogydd ymlaen llaw ac yna'i hawlio'n ôl gan Lywodraeth Cymru dros y cyfnod o 25 mlynedd?

Wedi'i ateb gan Gweinidog yr Amgylchedd, Ynni a Materion Gwledig | Wedi'i ateb ar 19/11/2019

Local Authorities participating in the Welsh Government’s Coastal Risk Management Programme (CRMP) will borrow upfront all of the funding required to pay for the design and construction of each project.

The Welsh Government will subsequently make annual payments to each Local Authority to cover the cost of capital and interest incurred over the 25 year duration of the loan, to a maximum of 75% of the total cost of the scheme.

This approach enables Local Authorities to utilise their borrowing powers to increase the total amount of capital funding available in Wales for coastal risk management and adaptation.