A wnaiff y Gweinidog ddarparu copi o'r ddogfen Cytundeb Grant a luniwyd rhwng Llywodraeth Cymru a Trafnidiaeth Cymru Trenau?
A copy of the Operator and Development Partner (ODP) Grant agreement has been published at the following link:
Supporting documents can be found at:
https://www.tfw.gov.wales/projects/wales-and-borders-rail-service#documents
The Transport for Wales ODP Grant Agreement outlines ODP obligations to deliver new Treforest Estate and Gabalfa stations by 31 October 2025 and 31 March 2027 respectively, using funding provided through the agreement. It also includes commitments to spend a minimum sum on other assets if planning permission isn’t granted. New stations at Crwys Road, Loudoun Square and Cardiff Bay should be completed with secure station accreditation by the target date of 31 March 2024
Transport for Wales are delivering Bow Street station on our behalf, and are working to complete construction in 2020.