WAQ70921 (e) Wedi’i gyflwyno ar 06/09/2016

A wnaiff y Gweinidog gadarnhau'r dyddiadau dechrau a gorffen ar gyfer uwchraddio Five Mile Lane, ac a yw'r gorchymyn prynu gorfodol a chaffael tir wedi cael ei gyflawni erbyn hyn? Os nad ydyw, pryd y mae'n disgwyl i hyn ddigwydd?

Wedi'i ateb gan Ysgrifennydd y Cabinet dros yr Economi a'r Seilwaith | Wedi'i ateb ar 15/09/2016

A formal planning application has been submitted and a decision is expected by this November. The Compulsory Purchase Order process has commenced and is at "consideration of objections" stage. The statutory processes could take up to a further nine months. If the statutory processes are successful, the forecast start date for construction is September 2017 with a 12 month construction period.